Installation Steps for Preformed Double-Grip Dead-End Clamps

Jun 20, 2026 Leave a message

Li Wei
Li Wei
As a senior technical expert at Shandong Fuhua Electric Power Equipment Co., Ltd., Li Wei specializes in the design and development of OPGW optical cables. With over 8 years of experience in the industry, he has contributed to multiple successful projects and is passionate about sharing insights on cutting-edge technologies in power equipment.

Installing preformed double-grip dead-end clamps does not require heavy equipment like hydraulic presses; a skilled worker can complete the process by hand. However, the installation demands high precision-particularly regarding the alignment of color codes, which directly affects the clamp's holding strength. The standard installation procedure is as follows:

 

Step 1: Preparation and Marking

 

Before installation, verify that the clamp and its accessories (inner helical rods, outer helical rods, U-shackles, extension links, thimbles, etc.) are complete, undamaged, and correctly sized. Clean the surface of the conductor or optical cable to ensure it is free of oil, dust, and other impurities.

Next, thread the outer helical rods through the thimble and align them parallel to the conductor. Align the color code (colored mark) on the outer rods with the installation reference point on the conductor or cable and mark it clearly. This mark serves as the baseline for installing all subsequent helical rods.

 

Double Layer Preformed Dead End

 

Step 2: Wrapping the Inner Helical Rods

 

Align the installation color code on the inner helical rods with the mark on the conductor, then wrap them systematically from the center outward toward both ends. Note:
The wrapping direction must be opposite to the lay direction of the conductor's outer strands. The rods must be wrapped tightly in a single pass to ensure a snug fit against the conductor; unwrapping and re-wrapping is not permitted.
Ensure the helical rods do not cross each other and maintain uniform spacing.
A small amount of slack may be left at the ends to facilitate subsequent steps.

 

Step 3: Wrapping the Outer Helical Rods

 

Thread the outer helical rods through the thimble and align their color code with that of the inner rods. Wrap one end for 1–2 pitches, then the other end for 1–2 pitches. Afterward, wrap both ends simultaneously until completion, ensuring uniform spacing between the rods. For the final two pitches, the rods may be separated during wrapping to ensure the ends seat correctly in place.

 

Step 4: Securing Connection Hardware

 

Assemble the connecting hardware-such as the thimble, U-shackle, and extension link-tighten the bolts, and install the cotter pins. Ensure the bolts are inserted in a consistent direction and that the cotter pin legs are spread at an angle of 60° to 90°.

 

Installation Precautions

 

Please also note the following during installation: strictly avoid using tools directly on the cables to prevent scratches or damage; ensure the lay direction of all preformed rods is consistent (standard is right-hand lay); verify the holding strength and connection reliability after installation; and do not reuse preformed rods more than twice.